TENTATIVE TIMETABLE & KEY FUTURE DATES
|
|
| |
|
|
November 2005
|
|
-- Shaft sinking completed into the mine area
|
|
|
| |
|
| December 2005 |
|
-- Shaft construction completed, hoist installation begins
|
|
-- Underground area preparation begins
|
|
|
| |
|
| June 2006 |
|
-- Site Work begins
|
|
-- Hoist Installation Complete
|
|
-- 85% Completion of Capital Campaign (goal)
|
|
|
| |
|
|
August - December 2006
|
|
-- Visitor Center construction begins
|
|
-- MSHA training for staff
|
|
-- Parking lot constructed
|
|
-- MSHA Safety Training for all staff completed
|
|
-- Exhibit Installation Begins
|
|
|
| |
|
| January 2007 |
|
-- Temporary Visitor's Center Completed
|
|
-- Advanced Group Reservations Accepted
|
|
|
| |
|
|
-- General Admission Tickets Available |
|
| -- Permanent Visitor's Center Construction Begins |
|
|
|
|
|
-- Permanent Visitor's Center Completed |
|
| |
|
| |
|
| |
|